Botley Road reopening Oxford MP ‘furious’ as delay confirmed

Published

on


The road, which is a key access route into the city, closed in April 2023 for £237 million railway bridge works to upgrade Oxford Station and was set to reopen next month.

Now, Network Rail has confirmed a further four – six-week delay for reopening.

The road has been shut off to traffic for almost three years and three months – it was initially supposed to close for 12 months. 

Oxford West and Abingdon MP, Layla Moran (Lib Dem) says she has written a “furious letter” to the Transport Secretary demanding answers and requesting an urgent meeting. 

She said: “Weeks more delay is calamitous and catastrophic for local residents and businesses. Time and again we have seen the goalposts move and promises broken.

“I am demanding a full explanation from the Secretary of State as to why these issues were not identified earlier, when those responsible first became aware of them, and why assurances about reopening have once again proven unreliable.

(Image: Oxford Mail)

“I already had serious questions about oversight, project management, risk identification and accountability.

“This latest delay only makes me more determined to get answers for long-suffering residents.”

The Liberal Democrat MP has continuously pushed both Network Rail and the Government to “get a grip” of the project previously.

She said that at every monthly progress meeting previously, Ms Moran was assured that all milestones had been hit and that the project was on track to open in August. 

Oxford East MP, Anneliese Dodds (Labour), said: “The news that the Botley Road reopening is yet again delayed will come as a bitter blow for local residents and businesses.

“It is particularly galling as every milestone had been hit by the project since January last year.

“It’s right they’ve been upfront about the unexpected gas main problem today.

“However, the daily impact on local peoples’ lives caused by the delays, even when unavoidable, has been dreadful.

“I will keep pushing for this project to be finished as speedily as possible.”

Anneliese Dodds, MP for Oxford East, spoke out on the delayed reopening of Botley Road announced on Wednesday, July 22. (Image: Anneliese Dodds (Facebook))

Oxford East MP, Anneliese Dodds (Labour), added: “The news that the Botley Road reopening is yet again delayed will come as a bitter blow for local residents and businesses.

“It is particularly galling as every milestone had been hit by the project since January last year.

“It’s right they’ve been upfront about the unexpected gas main problem today.

“However, the daily impact on local peoples’ lives caused by the delays, even when unavoidable, has been dreadful.

“I will keep pushing for this project to be finished as speedily as possible.”

The county council also had assurances, and last month it announced traffic filters were set to go ahead on September 14 – this policy was dependent on the reopening of the Botley Road, and the delay throws the start date for that scheme and the end of the congestion charge into the lurch.

Reopened Botley Road pathway (Image: Isabella Harris)

In its delay announcement, Network Rail explained that during excavation work relating to drainage for the new road, three minor gas leaks were identified on part of the gas network, owned by Southern Gas Networks (SGN).

SGN will now have to make repairs to the gas supply, delaying the finishing of the road.

Network Rail Great Western Route’s capital delivery director, Tim Walden, said: “We know this news will be deeply disappointing for residents, businesses and everyone who relies on Botley Road, and we’re very sorry for the continued disruption and uncertainty this will cause.

“Our teams, across SGN and Network Rail, are working as hard as possible to complete the remaining work and minimise delays, while keeping the community informed with regular updates.

“We expect the additional work to take around four to six weeks and are currently working on a plan so we can confirm the timings as quickly as possible.”

Botley Road area residents were informed of the delayed reopening decision tonight (Wednesday, July 22) at a community meeting on the Osney Mead Industrial Estate.

Network Rail was contacted for comment.





Source link

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Oxford News

Cotswold archaeologists uncover 1,500 year old Roman artefact

Published

on


The mosaic was found within a fourth century AD Roman Villa.

Archaeologists have been digging on farmland between villages in Devon after Roman remains were found by a metal detectorist in 2004.

READ MORE: Thames Water Oxfordshire hosepipe ban: Check who is exempt

The borders of the mosaic and a series of overlapping squares feature a twisted braid pattern, known as guilloche, which commonly features on Roman mosaics. // A Roman villa complete with a bath house, plunge pools and a rare flower mosaic has been uncovered beneath Devon farmland. Archaeologists have been digging on farmland between the villages of Halberton and Sampford Peverell, in Devon, led by teams at the University of Exeter and Cotswold Archaeology. Now in its second year, the five-year Saving Halberton's Ancient Roman Environment (SHARE) project is steadily revealing the hidden Roman site. The latest discovery, tiny 12mm square stone cubes which form a rare mosaic, are believed to have covered the floor of one of the villa’s rooms.The borders of the mosaic and a series of overlapping squares feature a twisted braid pattern, known as guilloche, which commonly features on Roman mosaics. (Image: Saving Halberton’s Ancient Roman Environment)

The latest discovery was a rare mosaic which features a flower pattern formed with tiny squares and centred with eight teardrop-shaped petals.

The mosaic is formed of thousands of red, white and dark blue cubes and would have been a decorative floor feature of the villa when it was thought to have been installed sometime in the fourth century A.D.

The string of elaborate discoveries, such as a bathhouse with at least two plunge pools, has led experts to believe the villa belonged to people of wealth and status.

READ MORE: Witney McDonald’s granted 24-hour application despite opposition

The borders of the mosaic and a series of overlapping squares feature a twisted braid pattern, known as guilloche, which commonly features on Roman mosaics. // A Roman villa complete with a bath house, plunge pools and a rare flower mosaic has been uncovered beneath Devon farmland. Archaeologists have been digging on farmland between the villages of Halberton and Sampford Peverell, in Devon, led by teams at the University of Exeter and Cotswold Archaeology. Now in its second year, the five-year Saving Halberton's Ancient Roman Environment (SHARE) project is steadily revealing the hidden Roman site. The latest discovery, tiny 12mm square stone cubes which form a rare mosaic, are believed to have covered the floor of one of the villa’s rooms.The borders of the mosaic and a series of overlapping squares feature a twisted braid pattern, known as guilloche, which commonly features on Roman mosaics. (Image: Saving Halberton’s Ancient Roman Environment)

The mosaic’s interlaced squares also form a common Roman pattern of a pair of knotted lines.

Other items found on the site were a delicate copper alloy bangle sitting on top of the mosaic, and a fine silver-plated spoon was unearthed in one of the villa rooms.

Cotswolds Archaeology has been working with the University of Exeter to uncover the site.

Project lead Dr Susan Greaney, of the University of Exeter’s Department of Archaeology and History, said: “At the outset, we knew this villa, and its surrounding working areas, was an important site for understanding the ‘Romanisation’ of Devon.

“But from day one, it has offered us a wealth of interesting and sometimes surprising finds in addition to this striking polychrome mosaic. We did not expect to find such an elaborate bathhouse, for example. This villa was undoubtedly home to people of wealth and high standing.”

 





Source link

Continue Reading

Oxford News

Oxford congestion charge may stay as Botley Road reopening delayed

Published

on



Network Rail confirmed today that the major road in the city will remain closed beyond the end of August.

The reopening of Botley Road had been planned for the end of August when the programme, involving the upgrading of Oxford Station and local infrastructure, was reviewed and amended in January 2025 to prioritise the reopening of the road to traffic.

However, during excavation work relating to drainage for the new road, three minor gas leaks were identified on part of the gas network, owned by SGN.

READ MORE: Nine ways to save your garden amid Thames Water’s hosepipe ban

The pipe was not damaged by the Network Rail work.

In the interests of safety, and to avoid disruptive and unplanned work to repair potential gas leaks in the future, Network Rail has agreed to accommodate work by gas distribution company SGN to replace a section of their network beneath Botley Road, as well as completing existing Network Rail work.

A statement from Oxfordshire County Council said: “Earlier this month the council announced that the traffic filter trial would replace Oxford’s temporary congestion charge on 14 September.

“Clearly this will not happen now, as the traffic filter trial will only begin after Botley Road has reopened.”

READ MORE: Police close Oxfordshire road after serious rush hour crash

Councillor Gareth Epps, Oxfordshire County Council’s Cabinet Member for Transport Management, added: “This is frustrating news for residents and businesses who have endured this closure for far too long as it is.

“We will continue to work with Network Rail and other partners to ensure the road can be reopened at the earliest possible time.

“As Network Rail has not released a revised opening date for Botley Road, we currently cannot say when our traffic filter trial will start, and the temporary congestion charge will end.

“We will make an announcement in due course, once we can be certain about the reopening.”





Source link

Continue Reading

Oxford News

Nine tips to save your garden amid Thames Water’s hosepipe ban

Published

on



The temporary water ban commences at 12.01am tomorrow morning (Thursday, July 23) and affects Oxfordshire.

Gardeners across the region are being urged to rethink how they care for their plants during the current dry spell.

The ban, affecting 10.1 million customers after an “exceptionally warm and dry spring”, means hosepipes should not be used for watering gardens or allotments.

READ MORE: Water pipe bursts just hours before Oxfordshire hosepipe ban

The water company said its region had seen 40 per cent of average rainfall, and more days at or above 34°C this year than ever recorded before.

While hosepipes may be off limits, there are still plenty of simple ways to keep gardens healthy while using water responsibly.

1. Water smarter, not more

If you’re using a watering can, water early in the morning or later in the evening when temperatures are cooler.

This reduces evaporation and allows more water to reach plant roots where it’s needed most.

Products containing wetting agents can also help water penetrate compost more effectively.

2. Prioritise the plants that need it most

Focus your watering on newly planted flowers and vegetables, young shrubs, containers and hanging baskets.

Established trees, mature shrubs and lawns are generally much more resilient and can recover once wetter weather returns.

3. Don’t panic if your lawn turns brown

A brown lawn isn’t necessarily a dead one. Most established lawns naturally go dormant during prolonged dry weather and will quickly green up again after rainfall.

Avoid watering unless you’ve recently laid new turf or sown fresh grass seed, and always check the specific exemptions under your local hosepipe restrictions.

4. Mulch to retain moisture

Applying bark, compost or other organic mulch around plants helps lock moisture into the soil, keeps roots cooler and reduces weed growth, meaning less water is lost through evaporation.

5. Stay on top of weeds

Weeds compete with your plants for valuable water and nutrients.

Removing them regularly ensures the moisture you do use benefits the plants you actually want to grow.

6. Feed plants wisely

Healthy, well-fed plants develop stronger root systems and are better equipped to cope with drought.

Follow product instructions carefully and avoid over-feeding during periods of extreme heat.

7. Make every drop count

Collect rainwater wherever possible using water butts and reuse suitable grey water, such as cooled cooking water or water used to rinse fruit and vegetables.

Avoid using any water containing detergents, bleach or harsh cleaning products.

8. Give containers extra care

Pots and hanging baskets dry out far more quickly than garden borders.

Grouping containers together in a partially shaded area can help reduce moisture loss during heatwaves.

If compost has become extremely dry, something that may happen more readily with peat-free composts, immerse the pot or basket in a container of clean water until air bubbles stop rising. This allows the compost to fully rehydrate.

9. Help plants cope with heat stress

Seaweed-based plant feeds can improve plants’ resilience during periods of drought and heat stress.